OEM
Implementation Plan
PHASE
I – Implementation on MKE Dev/Test systems & Migrate York OEM
1.1. Plan & Infrastructure setup
1.1.1
Discuss
the plan details with Richard and make changes as advised. Review the plan with
Team and solicit feedback. 09/05 – 09/06
1.1.2
List
all the dev servers and make assignments for agent deployment and config 09/06- 09/07
1.1.3
Prepare
Project monitoring sheet. This will have each server/assignee listed and with
various status columns to indicate progress of tasks. 09/07
1.1.4
Procure
server and disk 09/06 – 09/08
1.1.5
Install/Configure
OEM production instance .
09/11 -09/15
1.2. Agent Deployment & Target
configuration
1.2.1
Prepare agent deployment/config procedure. 09/12
1.2.2
Deploy OEM agent and configure for monitoring on all dev/test targets. All Team 09/18 – 09/22
1.3. YORK OEM Migration
– Dev systems S 09/18 – 10/07
1.3.1
Review OS Patch requirements
1.3.2
Schedule downtime with users for OS patching
1.3.3
Patch OS
1.3.4
Inventory the current OMS repository
1.3.5
Install IA on servers
1.3.6
Migrate Jobs
1.3.7
Post Migration Support
1.4. YORK OEM Migration – Prod systems S 10/16 – 10/28
1.4.1
Schedule downtime with users for OS patching
1.4.2
Patch OS
1.4.3
Install IA on servers
1.4.4
Migrate Jobs
1.4.5
Post Migration Support
1.5. Migrating Cron Jobs
1.3.1
Prepare job scheduling procedure. 09/19
1.3.2
Migrate monitoring/notification cron jobs All Team
09/25 – 09/27
1.3.3
Migrate any other oracle cron jobs All Team 09/27 –
09/29
1.6. Reconciliation with OVM
1.4.1
Review monitoring and notification metrics with Enterprise monitoring team as
there is an overlap of OEM and OVM 10/09 – 10/11
PHASE
II – Implementation on Production systems All Team
10/02 – 10/13
2.1 Agent Deployment & OEM Configuration
for monitoring All Team 10/02 – 10/06
2.2 Migrate cron jobs All
Team 10/09 – 10/13
2.3 Reconciliation
with OVM 1
PHASE
III – Add-ons and Improvements All Team 10/16 –
10/27
3.1
Policy violations
3.2
Reporting capabilities
3.3
Automation
3.4
Fixit jobs
BACKUP
?? – It more than deserves to be its own project.
Adhoc
1.
Update the -BE oracle standards for OEM and update Live Link